SpaceX said on Thursday that it will remove the unpermitted turbines powering its xAI data centers near Memphis as it transitions to a permanent, 1.2 gigawatt natural gas power plant. 

The turbines won’t be completely removed until July 2027, though. SpaceX said that it’s currently operating 69 gas turbines to power the Colossus data centers, of which many have been operating for months. The NAACP and Southern Environmental Law Center have sued xAI over the use of unpermitted turbines. SpaceX acquired xAI in February. 

In its IPO filing, SpaceX said it plans to buy $2.8 billion worth of gas turbines for its data centers over the next three years.

SpaceX claims that it is allowed to operate the existing turbines without permits because they remain on the trailers they were shipped on. But federal regulations say that the turbines xAI has been using, regardless of what they sit on, require permits because of their size and how they’re being used.

The turbines are currently located south of Memphis in Mississippi, just over the border with Tennessee. The region is among the most polluted in the U.S., and xAI has been operating gas turbines that have the potential to emit more than 2,000 tons of smog-forming NOx per year.

Last month, the Department of Justice sided with SpaceX in the NAACP’s lawsuit, saying the unpermitted turbines were a matter of “national, economic, and energy security.”

The new power plant that SpaceX is building will consist of 41 gas turbines ranging in size from 16.48 megawatts to 50 megawatts, according to permit documents issued by the state of Mississippi. They appear to be different from those currently in use, though TechCrunch could not verify the specific models of the 69 existing turbines.

Earlier this year, Elon Musk bought APR Energy, a company that specializes in temporary natural gas power. Based on an archive of the company’s site before it was taken down, the turbines in the company’s fleet also appear to be different from those cited in permits for the new, permanent power plant. 

Given that APR Energy’s turbines aren’t likely to be part of the new Colossus power plant, the new turbine fleet is likely intended for another, unannounced project.

When you purchase through links in our articles, we may earn a small commission. This doesn’t affect our editorial independence.



Source link

  • Related Posts

    OpenAI Is Building A Humanoid Robot, But The Body Isn’t The Real Challenge

    Figuring out how the ‘brain’ will work will take a lot of time. While OpenAI is already busy with the development of AI models and new consumer hardware, CEO Sam…

    Continue reading
    Wordle Hint Today: Answer for Oct. 18, #1947

    Looking for today’s Wordle answer? We’ve got Wordle hints first, then today’s answer for NYT Wordle No. 1,947 for Sunday, Oct. 18, 2026. Today’s Wordle might be tricky. It’s a…

    Continue reading

    Leave a Reply

    Your email address will not be published. Required fields are marked *

    You Missed

    OpenAI Is Building A Humanoid Robot, But The Body Isn’t The Real Challenge

    OpenAI Is Building A Humanoid Robot, But The Body Isn’t The Real Challenge

    WATCH: David's Bridal puppy collection

    WATCH:  David's Bridal puppy collection

    Wordle Hint Today: Answer for Oct. 18, #1947

    Wordle Hint Today: Answer for Oct. 18, #1947

    Sarkisian: Texas to ‘evaluate everything’ after loss to Florida

    Sarkisian: Texas to ‘evaluate everything’ after loss to Florida

    Metal band Genitorturers allegedly claims a Vampire: The Masquerade – Bloodlines remake is coming, getting a dozen crusty nerds way too worked up

    Metal band Genitorturers allegedly claims a Vampire: The Masquerade – Bloodlines remake is coming, getting a dozen crusty nerds way too worked up

    How US Legacy Carriers Fly For The Pentagon: The Civil Reserve Air Fleet Explained

    How US Legacy Carriers Fly For The Pentagon: The Civil Reserve Air Fleet Explained