Dredging of Vancouver’s Burrard approved to make room for big oil tankers


An aerial shows an oil tanker anchored in Burrard Inlet just a short distance from Kinder Morgan’s Trans Mountain marine terminal, top left, in Burnaby, B.C., is shown on Tuesday, May 29, 2018. THE CANADIAN PRESS Jonathan Hayward – The Canadian Press

VICTORIA — The Vancouver Fraser Port Authority says it has received all federal permits to allow for the dredging of Vancouver’s Burrard Inlet, making room for larger oil tankers loading up from the Trans Mountain pipeline.

The agency says the dredging along northern and southern edges of the navigation channel underneath Vancouver’s Second Narrows bridge will start in September, but it could not say how long the work will take.

The authority responsible for Canada’s largest port says the work is being done, so the ships — including Aframax-class tankers — filling up at the Westridge Marine Terminal can “load more fully.”

The Aframax ships measure up to 250 metres long and have a draft of up to 16 metres, but Trans Mountain says on its website that such tankers generally load to about 80 per cent of capacity in order to clear the inlet.

Prime Minister Mark Carney first floated the idea of dredging Burrard Inlet in the spring 2025, but the most recent federal budget does not include any specific references to the project, beyond promises to “improve access” to overseas markets by investing in new airport, railway and port infrastructure.

B.C.’s government also supports the project, and Energy Minister Adrian Dix said last year that the federal project “would allow for less traffic at the port and better utilization” because ships could fully load.

The port says the work will not change the number or size of the largest vessel type currently sailing underneath the Second Narrows, noting that Aframax-class tankers will remain the largest vessels.

The dredging comes about two years after the expanded TMX pipeline started operating in May 2024 and there have been calls to expand it again to help diversify energy exports away from the United States during recent trade friction.

Vancouver’s port authority say it is committed to carrying out the work with care for the environment and in collaboration with local communities and First Nations, noting that project is subject to more than 50 conditions.

They include measures to monitor and protect marine life and enhance kelp habitat.

Vancouver Fraser Port Authority also says it will limit all work in the water to the least-risk window for fish and fish habitat from mid-August to the end of February, as established by the Fisheries Department.

The environmental group the Sierra Club says the dredging project beneath the Second Narrows Bridge could undo “years of ecological healing” in the Inlet by disturbing toxic sediments and harming returning eelgrass, herring, salmon, seal, and whale populations.

The port authority says a low risk of contaminated sediment being disturbed during dredging and harming the marine environment exists but adds that the dredging contractor will be required to monitor turbidity to inform work pauses as needed.

A background document from the agency says most dredging will occur to a depth of around 1.3 metres to a maximum of six metres below the sea floor, removing about 25,000 cubic metres of material.

It says that is less than one per cent of the material the port authority removes annually from the Fraser River as part of a maintenance dredging program.

The project also calls for the removal of sections of two decommissioned Metro Vancouver waterlines and the installation of navigation aids.

This report by The Canadian Press was first published June 24, 2026.

Wolfgang Depner, The Canadian Press



Source link

  • Related Posts

    Vinícius analiza el renacer de Brasil y su momento personal: “Recuperamos nuestra identidad”

    IE 11 no es compatible. Para una experiencia óptima, visite nuestro sitio en otro navegador. SIGUIENTE Voces del Mundial: Ancelotti celebra ‘jogo bonito’ de Brasil y Escocia lamenta sus propios…

    B.C. penalizes helicopter firm after whistleblower details illegal dumping following glacier crash

    A whistleblower report led B.C. to penalize Alpine Helicopters after it crashed in Banff National Park and then dumped fuel and crash debris on Crown land Source link

    Leave a Reply

    Your email address will not be published. Required fields are marked *

    You Missed

    Vinícius analiza el renacer de Brasil y su momento personal: “Recuperamos nuestra identidad”

    Vinícius analiza el renacer de Brasil y su momento personal: “Recuperamos nuestra identidad”

    Former Infosys chief has a new startup that wants to challenge the IT services world

    Former Infosys chief has a new startup that wants to challenge the IT services world

    The Modern Engines Rewriting The Rules Of What A Narrowbody Engine Can Do

    The Modern Engines Rewriting The Rules Of What A Narrowbody Engine Can Do

    B.C. penalizes helicopter firm after whistleblower details illegal dumping following glacier crash

    B.C. penalizes helicopter firm after whistleblower details illegal dumping following glacier crash

    Judge wants to know why Kennedy Center facade has been covered since Trump’s name removed

    GTA 6’s preorders mark the start of a long wait for it to come to PC, despite the fact we’ll likely make up ‘50% of the sales’

    GTA 6’s preorders mark the start of a long wait for it to come to PC, despite the fact we’ll likely make up ‘50% of the sales’