The timelines, issued by the government’s Central Electricity Authority, will align generation and last-mile distribution projects with the grid, helping avoid delays. High-voltage direct current, or HVDC projects are required to complete in a maximum 54 months, while a 765 kilovolt substation should be built in three years, according to the advisory. Projects in hilly terrains may be allowed a longer construction period, the CEA said.